Your team is in its second month of development.You are managing a software development project for a banking product.In one of the team meetings a debate arises if defects found during Quality control need to undergo change control.Some team members are convinced that all defects should undergo change control while the other half is convinced that defects do not need to undergo change control.Which of the following statements are untrue ?
A. Defects to deliverables need to undergo change control
B. Defects to deliverables need not undergo change control
C. Corrective actions need to undergo change control
D. Preventive actions need to undergo change control
你的團隊正處于開發(fā)的第二個月。你正在管理銀行產品的軟件開發(fā)項目。如果在質量控制過程中發(fā)現的缺陷需要進行變更控制,在其中一次團隊會議中出現了一場辯論,有些團隊成員確信所有人缺陷應該進行變更控制,而另一半則認為缺陷不需要進行變更控制。下列哪些陳述是不真實的?
A.缺陷交付物需要經過變更控制
B.缺陷交付物不需要進行變更控制
C.糾正措施需要進行變更控制
D.預防措施需要進行變更控制
參考答案:B
解析:針對可交付成果的缺陷,采用糾正措施或預防措施都需要進行變更控制。因此,除了選項B之外,所有上述說明均屬實。參考PMBOK96。