After a product is released for user acceptance testing, several defects are found. This
results in the product being rejected by the customer,What should the project manager do next?
A. Review the quality management plan using the defect analysis acceptance testing, and
update if necessary.
B. Advise the customer that the defects are within the product tolerance limits outlined in the
quality management plan.
C. Meet with the project team to review the product's requirement specifications.
D. Hold a project team meeting to identify the problems, the time of the occurrence, and why it
occurred.
在一個(gè)產(chǎn)品發(fā)布用于用戶驗(yàn)收測(cè)試后,發(fā)現(xiàn)了幾個(gè)缺陷。這導(dǎo)致產(chǎn)品被客戶拒收。項(xiàng)目
經(jīng)理下一步應(yīng)該怎么做?
A.審查質(zhì)量管理計(jì)劃時(shí)應(yīng)用缺陷分析驗(yàn)收測(cè)試(標(biāo)準(zhǔn)),并在必要時(shí)更新。
B.通知客戶,缺陷在質(zhì)量管理計(jì)劃中概述的產(chǎn)品公差范圍內(nèi)。
C.與項(xiàng)目團(tuán)隊(duì)開會(huì)審查產(chǎn)品的需求規(guī)范。
D.召開項(xiàng)目團(tuán)隊(duì)會(huì)議,識(shí)別問題、發(fā)生的時(shí)間以及為什么會(huì)發(fā)生。
答案:D
解析:遇到問題首先分析問題、識(shí)別原因、然后解決問題。
2019-05-31 每日一題
?著作權(quán)歸作者所有,轉(zhuǎn)載或內(nèi)容合作請(qǐng)聯(lián)系作者
【社區(qū)內(nèi)容提示】社區(qū)部分內(nèi)容疑似由AI輔助生成,瀏覽時(shí)請(qǐng)結(jié)合常識(shí)與多方信息審慎甄別。
平臺(tái)聲明:文章內(nèi)容(如有圖片或視頻亦包括在內(nèi))由作者上傳并發(fā)布,文章內(nèi)容僅代表作者本人觀點(diǎn),簡(jiǎn)書系信息發(fā)布平臺(tái),僅提供信息存儲(chǔ)服務(wù)。
【社區(qū)內(nèi)容提示】社區(qū)部分內(nèi)容疑似由AI輔助生成,瀏覽時(shí)請(qǐng)結(jié)合常識(shí)與多方信息審慎甄別。
平臺(tái)聲明:文章內(nèi)容(如有圖片或視頻亦包括在內(nèi))由作者上傳并發(fā)布,文章內(nèi)容僅代表作者本人觀點(diǎn),簡(jiǎn)書系信息發(fā)布平臺(tái),僅提供信息存儲(chǔ)服務(wù)。
相關(guān)閱讀更多精彩內(nèi)容
- 項(xiàng)目管理術(shù)語英漢對(duì)照表2018-7-20 A Abstract Resource 抽象資源 Abstraction...
- Question 1. You have been asked to conduct an audit of th...
- **2014真題Directions:Read the following text. Choose the be...
- A consultant is working on a Service Cloud implementation...
- Learning Objectives Describe the five project management ...