7、一場(chǎng)重要會(huì)議結(jié)束后,團(tuán)隊(duì)收到客戶的負(fù)面反饋,團(tuán)隊(duì)把問題歸因于獲得需求規(guī)范時(shí)所使用的方法上。項(xiàng)目經(jīng)理應(yīng)該做什么?
After an important meeting, the team receives negativefeedback from the customer. The team attributes this issue to the approach usedto obtain requirement specifications. What should the project manager do?
A:檢查相關(guān)方參與計(jì)劃
Check the stakeholder engagement plan
B:提供經(jīng)驗(yàn)教訓(xùn)知識(shí)庫
Provide a lessons learned repository
C:更新范圍管理計(jì)劃
Update the scope management plan
D:與團(tuán)隊(duì)一起核實(shí)驗(yàn)收標(biāo)準(zhǔn)
Verify the acceptance criteria with the team
正確答案:B
解析:PMBOK(6)P98-4.4管理項(xiàng)目知識(shí)。“獲得需求規(guī)范時(shí)所使用的方法”,問題經(jīng)發(fā)生了,盡量規(guī)避以后再次出現(xiàn)。選項(xiàng)A,問題的核心是用錯(cuò)了規(guī)范,而不是相關(guān)方的態(tài)度。選項(xiàng)C,情景里面沒有強(qiáng)調(diào)是哪一次會(huì)議,如果是收尾過程的會(huì)議,范圍管理計(jì)劃的更新將失去意義。選項(xiàng)D,情景中沒有提到驗(yàn)收標(biāo)準(zhǔn)存在問題,排除。
疑問:對(duì)這個(gè)題的答案設(shè)置不理解。問題已經(jīng)發(fā)生了,項(xiàng)目經(jīng)理“提供經(jīng)驗(yàn)教訓(xùn)知識(shí)庫”給誰呢?為什么要提供呢?說“更新經(jīng)驗(yàn)教訓(xùn)知識(shí)庫、將本次問題及發(fā)生的原因記錄進(jìn)經(jīng)驗(yàn)教訓(xùn)知識(shí)庫”還差不多。